| FLOOR PREPARATION AND POLISHING |
1400S Europa |
1600S Raptor |
1800S TITAN |
2400S COLOSSOS |
SUPER COLOSSOS |
| Glue sq ft/hr (m2/hr) | 75 – 150 (7 – 14) |
300 – 500 (28 – 46) |
600 – 1,000 (56 – 93) |
1,200 – 2,000 (111 – 186) |
2,400 – 4,000 (223 – 372) |
| Paint sq ft/hr (m2/hr) | 100 – 200 (9 – 18) |
500 – 1,000 (46 – 93) |
1,000 – 2,000 (93 – 186) |
2,500 – 4,000 (232 – 372) |
5,000 – 8,000 (464 – 743) |
| Epoxy sq ft/hr (m2/hr) | 75 – 150 (7 – 14) |
300 – 500 (28 – 46) |
600 – 1,000 (56 – 93) |
1,200 – 2,000 (111 – 186) |
2,400 – 4,000 (223 – 372) |
| Thinset sq ft/hr (m2/hr) | 150 – 300 (14 – 28) |
350 – 750 (32 – 70) |
1,500 – 4,800 (139 – 446) |
3,000 – 7,200 (279 – 669) |
6,000 – 14,400 (557 – 1338) |
| Concrete sq ft/hr (m2/hr) | 100 – 200 (9 – 18) |
600 – 1,200 (56 – 111) |
1,000 – 2,000 (93 – 186) |
2,500 – 4,000 (232 – 372) |
5,000 – 8,000 (464 – 743) |
| Grind & Polish sq ft/DAY 70–3,000 grit (m2/DAY) sq ft/hr (m2/hr) |
300 – 500 (28 – 46) 40 – 60 (4 – 6) |
1,000
(93) 150 (14) |
2,000 – 2,400 (186 – 223) 250 – 300 (23 – 28) |
4,000 – 4,800 (372 – 446) 400 – 600 (37 – 56) |
8,000 – 9,600 (743 – 892) 800 – 1,200 (74 – 111 ) |
| * | Please note all statistics include edging. Production numbers may vary according to surface conditions, diamonds used, operator, etc. |
| DIAMOND LIFE |
Plug 'N Go PCDs |
Plug 'N Go Super Brazed |
Plug 'N Go Metal Bond Segments |
Plug 'N Go Resins |
| Diamond Life* sq ft (m2) | 25,000 – 75,000 + (2323 – 6968 +) |
10,000 (929) |
10,000 – 30,000 (929 – 2787) |
5,000 + (464 +) |
| Avg. Cost/sq ft ($) | 0.05 – 0.10 | 0.11 | 0.05 – 0.09 | 0.03 |
| * | Average conditions on normal concrete. |